To Add a Schedule Attribute
-
In the Schedule dialog, click the Configure Project Task Grid icon.
The Project Schedule Attribute Configuration dialog opens.
-
Click Add and in the Attribute Display Name dialog, enter a name for the activity.
The Internal Name for the addition is TSK_UD_<name of activity you just added>.
-
Click OK.
The attribute is added to the Schedule dialog.